Thank you. Please excuse my voice, and thank you for providing me with an opportunity to update the committee on the progress that has been made since our last appearance, on 28 June 2017.
I can confirm that the project outturn cost range remains at £1.325 billion to £1.35 billion. The Queensferry crossing opened to traffic on 30 August 2017 as planned, and the four days of opening events gave nearly 70,000 people the opportunity to see the new bridge at close quarters. The Queensferry crossing experience walk across the new crossing took place on 2 and 3 September, with 97 per cent of those who were successful in the ballot process actually participating on the day, which is a remarkably high participation rate for a free event of such scale. It provided a wonderful opportunity for charity fundraising and more than £100,000 was raised through the JustGiving page for the event, in addition to the money that was raised for charities by individuals.
Participants recognised the truly historic nature of the event. People with connections to the area, and particularly to the bridges, travelled from far and near to be part of it. Many used the occasion as an opportunity to recognise their personal challenges, and I was humbled to hear so many stories of personal bravery and achievement—including those relating to marriage proposals. It all contributed to an extremely positive event that I am sure will in time become an important part of Scottish history.
The official opening took place on the morning of 4 September and was performed by Her Majesty the Queen, accompanied by the Duke of Edinburgh. The date was of particular local significance, in that it was the 53rd anniversary of the opening of the Forth road bridge in 1964. The weather on the day was not so favourable, but that provided a flavour of the challenges that the men and women who worked on the project had faced and overcome.
Opportunities to participate in the opening events were highly sought after. The five major events, which took place in the space of just over a week, were organised to meet unprecedented demand from the public, local MSPs and councillors, international and United Kingdom media, stakeholders, schools and local communities. Because of the high public demand for tickets for the Queensferry crossing experience—more than 226,000 people applied for 50,000 tickets—an additional schools and community day was arranged for 5 September, which gave more than 6,000 pupils, teachers and parents from the 13 schools nearest to the project the chance to walk across the bridge. It also provided an opportunity for local community groups to access the crossing in the afternoon and evening of that day. Face-to-face and social media feedback for all those events was extremely positive.
The event to light up the Queensferry crossing was organised specifically to thank the workers, and to showcase them alongside the iconic bridge that they were responsible for building. The spectacular videos and images from that event gained wide international media attention from, among others, CNN, The New York Times, Al Jazeera and the South China Morning Post. The extensive media coverage promoted Scotland and the three bridges as unique visitor destinations.
Overall, the events showcased the incredible achievement of the workforce and a new iconic Scottish landmark. Since August, the Forth road bridge viewing platform has welcomed more than 30,000 visitors. Initial evaluation shows that print media coverage alone generated additional advertising-value-equivalent coverage worth £1.2 million.
The new roads and Queensferry crossing reopened to traffic in the early hours of 7 September, and in the first few days the crossing was extremely busy. We believe that that was primarily because of bridge tourists, many of whom were observed crossing the bridge several times, which they did by looping around at the Ferrytoll and South Queensferry junctions. That caused some disruption to local traffic because of the unusual traffic patterns that it created.
We have been closely monitoring traffic flows throughout the period and I can report that, following the first two weeks of operation, traffic has settled down to more normal patterns that are consistent with the patterns that existed prior to the opening of the Queensferry crossing. It is worth reminding the committee that the project was originally designated as the Forth replacement crossing. It was designed to maintain traffic flows at least at 2006 levels, not to increase capacity. At that time, it was determined that any future traffic increases would be accommodated through use of the Forth road bridge as a public transport corridor.
The project has been opened to traffic in a phased manner. Following completion of the connecting roads at the north end of the Forth road bridge, that route was reopened to scheduled bus services on 13 October. The footprint of the temporary traffic management was subsequently reduced and the speed limit was increased from 40mph to 50mph on the Queensferry crossing and the approach roads on 6 November. The installation and commissioning of the intelligent transport system is going through its final stages on the scheme. Following removal of the remaining traffic management, the Queensferry crossing will have an increased speed limit of 70mph and the Forth road bridge will be opened to other buses, taxis and certain motorcyclists in December.
Works on the intelligent transport system and the structural health monitoring, as well as mechanical and electrical works, are continuing inside the bridge deck and the towers and piers. Regular handover meetings are being held with Amey, which is the Forth bridges operating company, to prepare it for taking over the operation and maintenance of the bridge and the approach roads.
Community relations with the north and south community forums—which are due to meet for the last time this evening—continue to be extremely good. The schools programme at the contact and education centre in South Queensferry, which has proved to be extremely popular, will continue to operate for the remainder of the academic year until June 2018, when its future use will be reviewed. To date, the project has hosted more than 75,000 visitors from around the globe, including 25,000 schoolchildren from across Scotland.
I thank the committee for giving me the opportunity to provide an update. Lawrence Shackman, Mark Arndt and I would welcome any questions that members might have for us.